Compacting Recycled Materials in Pavements and Fill

By Liam Brosnan
18/11/2026

Recycled Materials in Pavements and Fill: What Changes at the Compaction Stage?

By the end of January 2026, 7.0 million tonnes of recycled and reused materials had been used on Victoria’s Big Build projects since the Recycled First Policy began in 2020, according to the ecologiQ Supplier’s Guide. For civil contractors, recycled materials are already part of everyday infrastructure delivery.

The practical question is what happens when those materials reach the workface. If the specification allows crushed concrete, glass sand or reclaimed asphalt in place of conventional material, can the crew carry over its usual rolling approach?

Compacting recycled materials starts with understanding the actual blend. Meeting the required material specification does not automatically make an established moisture target or rolling pattern suitable.

Why recycled materials are showing up in your specs

Victoria’s Recycled First Policy requires tenderers on major transport projects to show how they will optimise the use of recycled and reused materials, within the levels allowed under current standards and specifications. Successful tenderers must then report against those commitments during delivery. That brings recycled material selection into procurement and construction planning, rather than leaving it as an optional substitution once work starts.

The national approach also centres on performance. In its 2022 framework for assessing recycled materials, Austroads sets a key principle: using recycled materials should not worsen engineering, environmental, health and safety, or road-user outcomes compared with conventional materials. Recycled content does not lower the standard the finished pavement must achieve.

For contractors, this creates two connected tasks. First, confirm that the proposed material suits the specified application. Then establish how it will be placed and compacted to deliver the required result. Material approval addresses the first task; construction planning and verification address the second.

Equivalent on paper, different under the drum

Victoria’s ecologiQ Road Infrastructure Reference Guide (January 2022) states that Department of Transport accredited recycled products meet the required quality and performance criteria. It also notes they compete well with quarry products on quality, price and availability. On paper, a compliant recycled product can fill the same specified role as a quarry product.

Under the roller, it may need a different construction approach. A grading describes the distribution of particle sizes. It does not, by itself, describe everything that affects how a material responds to water and rolling.

The permitted application also matters. The same guide sets different allowances for different pavement classes and material types. For crushed rock, it lists supplementary-material limits of 5% for Class 1, 10% for Class 2, 15% for Class 3 and 50% for Class 4, subject to the applicable requirements. Crushed concrete has its own allowances, which vary by class and application.

Those distinctions are worth resolving before ordering material. A limit on supplementary material within crushed rock is not permission to use any recycled product at that percentage. Where a blend contains more than one recycled material, check how the specification treats the combined total. The relevant state specification, registered mix and project requirements remain the reference points, and the guide itself notes it does not replace current Department of Transport standards.

The same discipline should carry through to the rolling plan. “Recycled roadbase” is a purchasing description, not a compaction procedure.

How recycled materials behave differently under the roller

Crushed concrete: account for water absorption

A review of recycled materials for unbound applications from the University of Wisconsin–Madison describes how residual mortar on crushed concrete increases water absorption compared with conventional aggregate. It also reports research in which optimum moisture content (OMC) rose as the crushed-concrete proportion increased. OMC is the moisture content at which a material reaches its maximum dry density for a given compactive effort. These overseas findings support using the blend’s own test results rather than carrying over a quarry-rock moisture target.

Crushed concrete: consider changes after watering

The review also identifies potential self-cementing behaviour: unhydrated cement exposed during crushing can react with water. The researchers note the actual effect is still to be determined. The practical step is to discuss conditioning, placement and compaction timing with the supplier and project team, rather than assuming every crushed-concrete product stays unchanged after wetting.

Reclaimed asphalt: establish the blend's moisture requirements

Reclaimed asphalt pavement, or RAP, contains bitumen-coated aggregate. Studies in the Wisconsin review found OMC fell as RAP content increased. That is not a universal instruction to add less water. The actual blend still needs testing.

Glass sand: familiar characteristics, specific requirements

Recycled glass sand presents a different picture. Austroads reports that good-quality recycled crushed glass sand generally has characteristics similar to natural sand. Processing and compliance are central to that statement: the product must be manufactured to suit its intended application, such as bedding, backfill or embankment fill.

For crews familiar with granular materials, that is a useful starting point. It still leaves the project team to confirm how the supplied glass sand, or the blend containing it, performs in the proposed layer. Similar material characteristics do not establish the finished blend’s rolling requirements.

At a glance

MaterialWhat’s differentWhat it means on site
Crushed concreteResidual mortar absorbs more water; OMC can rise with higher crushed-concrete contentSet moisture from the blend’s own tests, not a quarry-rock target
Crushed concreteExposed unhydrated cement may react with waterAgree conditioning and the timing between watering and rolling with the supplier
RAP (in unbound blends)Bitumen-coated particles; OMC fell as RAP content rose in overseas studiesTest the actual blend; don’t assume it always needs less water
Glass sandGood-quality product generally has similar characteristics to natural sandA familiar starting point, but still confirm performance in a trial
Crushed concrete and RAP findings are from US research; test your actual blend.

What to plan for on site

These steps help turn material approval into a clear construction process.

  • Start with the actual product and application. Confirm the supplier, blend designation, intended layer and supporting test information before mobilisation. Keep unbound pavement blends containing RAP separate from asphalt products made with RAP, and pavement material separate from general or selected fill.
  • Set the rolling procedure through a trial section. Use the intended material, lift thickness and roller, and record speed, vibration settings, moisture and pass sequence alongside the test results. Reassess the procedure when the source, stockpile or blend changes.
  • Make moisture conditioning part of the program. Get the moisture requirements and conditioning advice for the supplied product, based on the blend’s own tests. Agree who checks material before placement and who authorises adjustments, so the supplier, water-cart operator and roller operator work from the same target.
  • Match the roller to the material and lift. Roller mass, drum type, vibration settings, lift thickness and underlying support all affect the result. Where trial results stop improving, find the cause before adding passes: excessive vibratory rolling can break down particles and generate fines. Our guide to how many roller passes you need for proper compaction explains these relationships.
  • Keep process records and acceptance results connected. Testing confirms the result; the pass count records the process. Intelligent compaction, which uses roller-mounted sensors and satellite positioning to map passes and material response, shows coverage across the whole area and helps at operator handovers.

From trial results to an updated rolling target

A council car park project in South East Queensland, documented in a Conplant case study, shows how this works in practice. Völkel Intelligent Compaction was used on the project to assess the existing base and to track rolling.

The asphalt was a cold recycled product made from 100% reclaimed asphalt, with water and bitumen emulsion added to reactivate the binder. This is a manufactured asphalt product, distinct from RAP in an unbound pavement blend. It changed the compaction stage in clear ways. Working time was measured in hours rather than the roughly 20 minutes of hot mix, with a 12-hour window for rolling before the mix went off and hardened over about 48 hours. Because the layer was still soft after final rolling, the system’s stiffness readings were not used for it.

The project also showed the value of adjusting the rolling target from trial results. The initial target was four to six dynamic passes, meaning passes made with vibration operating. Once trial work began, the team found that target was higher than required and reduced it to four. The change was made in the Völkel web app on a smartphone and updated the operator’s display straight away. The operator was kept informed of the change and the reason for it.

Four passes was the outcome on that project, not a prescription for other materials.

The example also highlights a point for anyone reviewing records: changing a target changes how earlier work appears on the map. The trial area showed as over-rolled once the target dropped. Rolling data needs to be read alongside the procedure and decisions that applied at the time.

Planning the roller alongside the material

Conplant’s team can help match hire equipment to an unfamiliar recycled material, the planned lift and site conditions, and supply Völkel Intelligent Compaction for pass mapping. Bringing the material details and trial requirements into the equipment discussion gives the team a clearer basis for selection. If you’re planning work with a recycled blend, request a quote with those details so the roller can be considered as part of the construction plan.